Ho Chi Minh City to tackle public spending bottlenecks 

 Thursday, February 12,2026

AsemconnectVietnam - By the end of 2025, the city had disbursed 74% of the amount targeted by the Government – 89.07 trillion VND (3.7 billion USD) out of 120.32 trillion VND – well below the near-100 % rate typically required to maximise economic impact.

 Ho Chi Minh City is stepping up efforts to resolve the long-standing paradox of abundant capital but low public spending, which will continue to play a decisive role in sustaining growth in 2026 and subsequent years.


Despite improvements compared to previous years, public spending disbursement in 2025 fell short of expectations.

By the end of 2025, the city had disbursed 74% of the amount targeted by the Government – 89.07 trillion VND (3.7 billion USD) out of 120.32 trillion VND – well below the near-100 % rate typically required to maximise economic impact.

This persistent shortfall has remained unresolved for many years, limiting the effectiveness of public spending as a growth driver.

The city’s leaders noted that had public spending been more efficient, economic growth would not have been constrained to just over 8.03% in 2025, but could have reached a much higher rate.

Slow land clearance was identified as one of the major bottlenecks, underscoring the need for more decisive solutions to accelerate work.

Based on commitments from agencies, departments and project developers, the Department of Finance projects that by the close of the 2025 fiscal year on January 31, 2026, disbursement could rise to around 114.39 trillion VND (roughly 4.77 billion USD), or 95% of the plan.

January has been identified as a critical period to realise this target.

The department will continue reviewing and urging progress on projects with large disbursement volumes, while advising the city administration to promptly clear obstacles and ensure funds are released on schedule.

Priority will be given to major projects, with expected disbursement of 11.39 trillion VND (about 475 million USD), accounting for nearly 55% of the remaining capital to be released.

At a conference on implementing socio-economic tasks for 2026 held recently, Chairman of the municipal People’s Committee Nguyen Van Duoc acknowledged these shortcomings, saying stronger and more effective measures are required to decisively address the disbursement deadlock and create a solid foundation for growth in 2026 and beyond.

Drawing lessons from previous limitations, he said preparations for the 2026 disbursement plan have been accelerated from the outset.

Relevant departments are expected to complete all necessary procedures within the week to enable timely funds allocation and ensure projects are implemented according to plan from the beginning of the year.

The city has already approved its 2026 public spending programme, enabling agencies and investors to proactively develop detailed disbursement schedules and ensure full utilisation of allocated funds.

To meet the target, the department has urged departments, districts, special administrative units, and project developers to implement a coordinated set of solutions.

Top priority will be given to completing procedures to allocate the remaining capital of 18.4 trillion VND (767 million USD) in the first quarter of 2026, creating sufficient fiscal space for implementation throughout the year.

Monthly monitoring of every project will be intensified, with disbursement performance linked to emulation and performance assessments of officials.

Compensation, resettlement and technical infrastructure relocation will also be accelerated to ensure timely site handover, while local authorities mobilise grassroots political systems to build public consensus.

Notably, the city aims to shorten administrative processing time for investment procedures by at least 30%, promote digital tools for monitoring and management and closely track construction material markets to address supply and price fluctuations.

It will also adjust capital allocation, decisively cutting funds for delayed projects and reallocating them to those with strong implementation capacity, while concentrating resources on large, high-impact projects to enhance the overall effectiveness of public investment./.

Source: VNA

  PRINT     BACK


 © Vietnam Industry and Trade Information Center ( VITIC)- Ministry of Industry and Trade 
License: No 115/GP-TTĐT dated June 05, 2024 by the Ministry of Information and Communications.
Address: Room 605, 6 th Floor, The Ministry of Industry and Trade's Building, No. 655 Pham Van Dong Street, Nghia Do Ward, Hanoi city.
Tel. : (04)38251312; (04)39341911- Fax: (04)38251312
Websites: http://asemconnectvietnam.gov.vn 
Email: Asemconnectvietnam@gmail.com 
 

Hitcounter: 25739382750