Ca Mau Fertilizer Plant (DCM) completes master maintenance, returns to production
Thursday, October 22,2026
AsemconnectVietnam - After continuous implementation under unfavorable weather conditions, the 2026 master maintenance campaign of the Ca Mau Fertilizer Plant has been completed safely, ensuring quality and meeting the set schedule.
The plant officially returned to operation and began producing products again from October 7, 2026. More than 3,200 items were implemented during the 2026 master maintenance campaign of the Ca Mau Fertilizer Plant.
Master maintenance is one of the important tasks to maintain the reliability, safety, and stability of the Ca Mau Fertilizer Plant, while also creating a foundation for production in the next phase. During the implementation process, Ca Mau experienced several prolonged periods of heavy rain, significantly affecting construction and working conditions on the site. However, the work was still organized and strictly controlled according to plan. The participating forces maintained continuous coordination, proactively adjusting construction plans to suit actual conditions, and conducting safety checks before deploying each task, thereby ensuring progress without compromising safety.
Under the close guidance of PVCFC and the Plant's leadership, along with the cooperation of engineers, workers, experts, and contractors, the maintenance items were completed according to technical requirements. In particular, tasks of a critical nature to the overall progress were prioritized, implemented synchronously, and strictly controlled.
On the morning of October 5, 2026, the Ca Mau Urea Plant officially resumed operation, and by 2:00 AM on October 7, 2026, the plant had resumed production, marking the completion of the entire 2026 maintenance campaign and readiness for fertilizer production and supply to the market.
The completion of the 2026 maintenance and repair plan is a prerequisite for the Ca Mau Urea Plant to continue its new operating cycle with higher requirements for safety, stability, and efficiency, contributing to ensuring a supply of high-quality fertilizers for agricultural production.
Source: VITIC/Bao Tai chinh – Dau tu
EVF plans to raise $300 million in international bonds
EVNGENCO3 continues to promote new power source projects
DNSE sets a record for derivatives market share at 26.62% and maintains Top 2 position
Dat Phuong (DPG) wins construction contract worth over VND1.217 billion for Gia Binh airport connecting road project
OCH successfully raises VND1,300 billion to acquire shares in EDS Equity Holdings
VPS: Building a foundation, shaping the future
BIWASE (BWE): After-tax profit exceeds full-year plan in 9 months, Welcomes over 15,000 new connecting customers
Dien May Xanh (DMX) nears VND100 trillion in revenue
Vietnam Rubber Group (GVR) achieves approximately 99% of pre-tax profit plan after 9 months
Vinatex (VGT) reaches VND1,470 billion profit in 9 months, exceeding annual plan by 6.5%
Chuong Duong (CDC) intends to acquire 49% of a real estate company with a charter capital of VND600 billion
Hoa Phat (HPG) completes capital contribution, owns 25.13% of Tuong Lai Song Hong
Digiworld (DGW) surpasses $1 billion in revenue after 9 months, completing 84% of annual plan
Pomina Steel (POM) receives VND1,352 billion in capital support from Vinhomes (VHM)

Viet Nam seeks to expand space for ASEAN-China cooperation ...
Viet Nam expects to make greater contributions to expanding the space for ASEAN-China cooperation for shared prosperity, underlined ...Top leader To Lam to attend 81st UNGA General Debate, ...
Viet Nam treasures friendly relations with Thailand: Prime ...

Viet Nam approves action program to implement ASEAN ...
The Vietnamese Government has approved an action program to implement the ASEAN Connectivity Strategic Plan in Viet Nam for 2026–2035 ...Industry and trade sector steps up strategic technology ...
Gov't approves National AI Strategy
Viet Nam continues to strengthen its strategic position in ...